Emergency Ground Water Development Project (Akaki) - Summary
1. Project Overview
The Emergency Ground Water Development Project (Akaki) is a water supply initiative for Addis Ababa, Ethiopia, managed by the Addis Ababa Water and Sewerage Authority (AAWSA). The project aims to address critical water shortages by developing groundwater resources from the Akaki well field area to deliver approximately 52,000 m³/day of water to the southern half of the city.
2. Key Project Components
- Construction of 4 pumping stations and 5 reservoirs (2x1000m³ and 3x2500m³ capacity)
- Auxiliary structures (dwellings, generator house, guard house, parking lot)
- Supply and installation of 8km collector pipes, 23km transmission, and 25km distribution network
- Steel structure bridge for Akaki River crossing
- Associated electro-mechanical equipment
3. Consultancy Services
The Water Supply and Sewerage Agency (WSSA) with sub-consultant Metaferia Consulting Engineers (MCE) was appointed to provide:
3.1 Scope of Services
- Tender evaluation and contract award recommendations
- Preparation and review of working drawings
- Construction supervision and contract management
- Equipment inspection and testing
- Commissioning of waterworks
- Training and technology transfer
3.2 Key Personnel
| Position | Name | Key Qualifications |
|---|---|---|
| Project Director | Ato Mesfin Tegene | Overall project leadership |
| Project Engineer | Ato Goitom K/Giorgis | Civil engineer with MSc in Water Supply |
| Senior Water Supply Engineers | 3 specialists | Extensive water supply project experience |
| Electrical Engineer | Mr. Markku Repo | Finnish expert with international experience |
| Mechanical Engineer | Mr. Markus Anton Saari | Pumping station design specialist |
4. Contract Terms
4.1 Financial Terms
- Total contract ceiling: US$267,300 (foreign currency) + Birr 8,960,490 (local currency)
- Advance payment: 20% of contract amount
- Payment schedule: Monthly billing with 60-day payment terms
4.2 Duration
The consultancy services were planned for 30 months (including 6 months for tendering and 24 months for construction supervision). An optional 12-month extension was possible for the maintenance period.
4.3 Key Contract Clauses
- Force Majeure: Provisions for events beyond reasonable control
- Termination: Conditions for termination by either party
- Dispute Resolution: Amicable settlement followed by arbitration in Ethiopia if needed
- Confidentiality: 2-year confidentiality period after contract expiration
5. Organizational Structure
The project organizational chart shows:
- WSSA Project Director at the top
- AAWSA Project Engineer
- Project Engineer (Consultant)
- Contract/Office Engineer
- 3 Site Engineers
- Senior Water Engineer
- Short-term experts
6. Appendices Summary
| Appendix | Content Summary |
|---|---|
| A - Scope of Services | Detailed description of all consultancy services |
| B - Consultant's Services | Specific services and facilities to be provided by the consultant |
| C - Client's Services | Facilities and support to be provided by AAWSA |
| D - Work Programme | Detailed schedule of activities and personnel inputs |
| E - Remuneration | Payment structure and cost breakdown |
| F - Key Personnel | CVs of all proposed technical staff |
| G - Terms of Reference | Detailed technical requirements for the project |